We are RISQS approved rating 5 star
We are RISQS approved rating 5 star

Case Studies

Springbank West, Hull

This project was a railway bridge replacement over a busy road in and out of Hull.  Our contract was to build two abutment walls in front of the existing ones keeping disruption to the traffic at bare minimum.  Once the two walls were built the concrete had to cure for 28 days.  On boxing day over the Christmas period the old bridge was removed and the new one put in its place. As it was so tight for time Mcrail came up with the installation of the Peri formwork system to pour the walls in one pour which saved valuable man hours and a very tight program. We could not have achieved this by doing it with a traditional formwork system in the time given.  The finish on the concrete was a very high specification where an insitex liner was fixed to the face of the formwork  to form the pattern required. We finished on program and overcame numerous obsticals to achieve this.

Birmingham, New Street

The erection of a MegaDeck at the entrance to Birmingham New Street Station for Martifer.  This was quite a unique undertaking as the deck was erected above one of the main entrances to the Hub Station above the Taxi Rank, Entrance and Platform.

Ruislip Depot

McRail Constructions Ltd carried out works at Ruislip Depot on behalf of Clancy Docwra constructing new inspection pits and a reinforced concrete platform throughout the full length of the existing warehouse to cater for three separate tubes in a servicing capacity. 

Seven Sisters

For Spence rail, the main contractor was Volker Rail. It was an upgrade to the station involving platform possesion reinstating works, pedestrian walk way refurbishment, and general upgrade of station.

Our Companies

In order to visit us

McRail Constructions Ltd Canal Wharf

Horsenden Lane North Greenford 

Middlesex

UB6 7PH  

Please call us on

0208 903 2433

0333 9000 600

Print | Sitemap
© 2015 McRail Construction Ltd. All rights reserved. A company within the Cuig Group